Guide

MCC vs PCC panels

A PCC, or power control centre, receives power from the transformer or DG set and distributes it to large feeders and sub-panels. An MCC, or motor control centre, takes one of those feeders and controls and protects individual motors. Most plants need both, with one PCC feeding several MCCs close to the motor loads.

By Kulaina engineering team ·

What a PCC does

The PCC is the main LT panel. It takes the supply from the transformer and the DG set, usually through air circuit breakers, and splits it into outgoing feeders for sub-panels, MCCs, lighting boards and large single loads such as chillers or compressors.

What an MCC does

An MCC is built around motors. Each feeder carries a starter, such as DOL, star-delta, soft starter or VFD, with overload protection, interlocks and control wiring back to a PLC or control desk.

How they compare

PCC MCC
Job Distributes power across the site Controls and protects motors
Typical incomer Transformer and DG set A feeder from the PCC
Main devices ACBs and MCCBs MCCBs or MPCBs, starters, drives and overload relays
Typical location Main electrical room Near the motor loads

How plants combine them

A typical plant has one PCC in the main electrical room feeding several MCCs, one per production area. Placing each MCC near its motors shortens cable runs, and giving each production area its own MCC means a fault on one line does not take down the others.

See PCC panels and MCC panels for ratings and options.

Related products

Frequently asked questions

Can one panel be both a PCC and an MCC?

In a small plant, yes. A combined PCC-MCC has an incomer and distribution section plus motor starters in one lineup. Larger plants separate them so the MCCs can sit near the motors.

Which panel needs a higher fault rating?

The PCC, because it sits closest to the transformer where the available fault current is highest. MCCs further down the system usually see lower fault levels.

Discuss your panel requirement

Send your single-line diagram, BOQ or tender reference. An engineer replies within one working day.

Have drawings or a tender? Use the full enquiry form.