Kulaina supplied power distribution and motor control panels for a continuous-process opal-glass plant in Jaipur, where furnace-critical loads cannot stop. The panels were built, tested and commissioned around the plant's shutdown window, and the site has run without panel-related unplanned stops since commissioning.

PCC and MCC panels ready for dispatch
Client
Borosil Limited
Sector
Glass manufacturing
Panel
PCC panels
Rating
2500 A PCC with MCC sections
Timeline
6 weeks from order to commissioning
Result
No panel-related unplanned stops since commissioning
PCC and MCC panels ready for dispatchPanels installed in a plant electrical room

The challenge

A glass furnace runs around the clock. Any interruption to furnace-critical loads risks the melt, so the distribution system had to be replaced without disturbing production.

What we supplied

A Form 4 PCC feeding dedicated MCC sections for furnace blowers and conveyors, with draw-out feeders so individual circuits can be maintained live.

The result

The changeover was completed inside the planned shutdown window, and the plant has run without panel-related unplanned stops since.

Panel used in this project: PCC panels